Valeura Takes FID on Bussabong Gas Field Phase 1 in Thailand

  • Valeura Energy and PTTEP approved final investment decision for Phase 1 of Bussabong gas field development in Thailand's Gulf of Thailand.
  • Phase 1 includes two wellhead platforms with 24 slots each, tied to existing processing infrastructure via a 9 km pipeline.
  • Project capital expenditure estimated at $35 million for facilities and $20-25 million for drilling 25 development wells (Valeura's 40% share).
  • First gas production expected by year-end 2028, with initial output of 30 mmcf/d (12 mmcf/d net to Valeura).
  • Valeura's 40% non-operated working interest in Block G3/65 expected to be formally transferred by early October 2026.

Valeura's FID on Bussabong marks its first organic gas development in Thailand, leveraging PTTEP's operational expertise and existing infrastructure. The project aligns with Valeura's strategy to diversify its portfolio in Southeast Asia, with Phase 1 serving as a template for future development phases. The modest capital outlay and rapid development timeline reflect the strategic importance of the PTTEP partnership and the field's potential for long-term production growth.

Execution Risk
Whether Valeura and PTTEP can deliver Phase 1 on schedule and within budget, given the 2028 target for first gas.
Reserve Growth
The pace at which additional reserves will be added following the execution of a gas sales agreement and year-end 2026 evaluation.
Phased Development
How subsequent development phases will unfold, given the field's potential for further exploration and appraisal upside.