TeraWulf Doubles Power Capacity at Kentucky AI Campus to 1 GW
Event summary
- TeraWulf expanded contracted power capacity at its Muskie Data Campus from 500 MW to 1 GW.
- The second 500 MW phase delivery is accelerated to 2029 from 2030, pending regulatory approval.
- Muskie campus is being developed for AI and high-performance computing workloads.
- Kentucky Power is constructing a 765-kV / 345-kV substation to support the site.
- TeraWulf acquired Muskie in May 2026 for phased development.
The big picture
TeraWulf's expansion reflects the growing demand for AI and high-performance computing infrastructure, particularly in regions with robust power and regulatory support. The company's strategic focus on securing long-term power agreements and coordinating with utilities positions it to capitalize on the data center boom, though execution risks remain tied to regulatory timelines and customer acquisition.
What we're watching
- Regulatory Approval
- Whether the Kentucky Public Service Commission will approve the accelerated timeline for the second phase.
- Customer Demand
- How quickly TeraWulf can secure customers for the additional 500 MW of capacity.
- Infrastructure Scaling
- The pace at which Kentucky Power can develop the necessary substation and transmission infrastructure.