Soluna Secures ERCOT Base Load Status for Full 166 MW Kati Campus
Event summary
- Soluna completed its 83 MW Kati 1 phase, bringing total operating capacity to 206 MW.
- ERCOT conditionally classified the full 166 MW Kati campus as Base Load in its Batch Zero process.
- Kati 1 is dedicated to Bitcoin hosting, with Kati 2 planned for AI and high-performance computing.
- The project bypasses transmission upgrades by being built behind the meter with wind power.
- Soluna's development pipeline includes approximately 6.3 GW, with 650 MW for AI and HPC.
The big picture
Soluna's success in securing Base Load status highlights the growing importance of renewable-powered data centers in ERCOT's grid planning. With nearly 90% of interconnection requests coming from data centers, Soluna's model of co-locating with wind power positions it favorably in a congested market. The strategic shift to AI and HPC applications at Kati 2 reflects broader industry trends toward high-performance computing demands.
What we're watching
- Regulatory Confirmation
- Whether ERCOT will fully confirm the 166 MW Base Load status pending verification.
- Execution Pace
- The speed at which Soluna can deploy and fill capacity at Kati 2 and other projects.
- Market Positioning
- How Soluna's behind-the-meter model will perform against grid-connected competitors.