- NiSource signs 20-year energy agreement with Microsoft for its northwest Indiana data center campus, starting in 2028.
- Deal increases expected NIPSCO electric customer savings to $1.75 billion, up from $1.4 billion, with up to $140 annual savings per customer.
- Microsoft will fund all generation and transmission required to serve its load, adding 1,100 MW to GenCo’s pool portfolio.
- NiSource contracts 600 MW of battery storage under a long-term tolling agreement with AGP Group affiliate.
- Agreement aims to upgrade NIPSCO’s electric transmission system, improving grid reliability and resilience.
The big picture
NiSource’s deal with Microsoft underscores the growing trend of tech giants partnering with utilities to secure reliable, cost-effective energy for data centers while mitigating ratepayer impacts. This agreement reflects a strategic shift in how utilities balance economic development with customer affordability, particularly in regions like Indiana poised for significant tech investment. The inclusion of battery storage highlights the increasing role of energy storage in modernizing grid infrastructure.
What we're watching
- Execution Risk
- Whether NiSource can deliver the 1,100 MW capacity expansion and 600 MW battery storage on time and within budget.
- Regulatory Dynamics
- How regulatory approvals and public involvement may impact the timing and terms of the agreement.