NiSource Secures Regulatory Nod for Amazon Data Center Power Deal in Indiana

  • The Indiana Utility Regulatory Commission approved NiSource's settlement agreement with Amazon for data center power supply on June 17, 2026.
  • Approvals include a special contract and power purchase agreement, along with generation resources like combined-cycle gas turbines and battery storage systems.
  • NiSource expects $1.4 billion in customer savings over the life of the data center contracts under the approved framework.

NiSource's regulatory approvals underscore a strategic shift in utility-data center collaboration, positioning Indiana as a leader in tech infrastructure development. The model, where data center customers fund their own infrastructure needs while existing customers benefit from savings, could set a precedent for how utilities manage large-load growth amid rising demand for digital infrastructure.

Regulatory Speed
Whether NiSource can maintain expedited approval processes for future data center agreements.
Customer Savings
How the $1.4 billion in expected customer savings will materialize and impact bill credits.
Industry Precedent
The pace at which other utilities adopt similar models for large-load customer partnerships.