Mayfair Gold Advances Fenn-Gib Exploration with Drill-Ready Targets

  • Mayfair Gold completed 23 condemnation drill holes totaling 6,184 meters at Fenn-Gib, confirming site layout suitability.
  • Mapped 95% of known outcrops and collected 127 grab samples across North and South Blocks.
  • Advanced integrated 3D geological and multi-element geochemical model for broader property exploration.
  • Plans for early 2027 drilling program following summer exploration progress.

Mayfair Gold's systematic exploration advances at Fenn-Gib align with its strategy to develop the 4.3 million ounce indicated mineral resource into a scalable gold producer. The company's focus on high-grade near-surface reserves supports its path to production, with $450 million in initial development capital and a projected 2.7-year payback period. Success hinges on maintaining exploration momentum while navigating regulatory and stakeholder engagement timelines.

Drill Results
Whether early 2027 drilling confirms high-grade potential in South Block targets.
Geological Modeling
How the integrated 3D model refines exploration strategy across Fenn-Gib property.
Permitting Timeline
The pace at which permitting and engineering progress toward 2028 construction start.