Lithium Ionic Advances Bandeira Project with Long-Lead Order and Community Engagement

  • Lithium Ionic placed its first long-lead order for Bandeira’s main substation power transformer from Brazilian manufacturer Blutrafos.
  • Overall engineering for the Bandeira project has advanced to 65% completion since the Feasibility Study released on September 17, 2025.
  • Geotechnical drilling (1,352m) completed to support detailed engineering and design.
  • Over 4,500 personnel hours spent in community engagement near Bandeira since late 2025, with 700 attendees engaged to date.

Lithium Ionic's progress at the Bandeira project reflects the broader trend of lithium developers advancing hard-rock lithium projects in Brazil's 'Lithium Valley.' The strategic focus on de-risking the project through engineering and community engagement aligns with the growing emphasis on responsible resource development in the global battery supply chain. The company's transition into the procurement and execution phase marks a critical step toward becoming a near-term producer of high-quality spodumene concentrate.

Execution Risk
The pace at which Lithium Ionic can secure additional long-lead items and advance procurement will determine the project's schedule certainty.
Community Relations
Whether the company can sustain positive community engagement as the project moves toward construction will be critical for social licensing.
Procurement Strategy
How the company's focus on local hiring and shared prosperity will impact operational timelines and costs.