i-80 Gold Reports High-Grade Assay Results from Archimedes Underground

  • i-80 Gold announced additional high-grade assay results from the Archimedes Underground Project, including 16.2 g/t Au over 56.4 meters.
  • The company updated the timing of feasibility-level technical studies for Granite Creek and Cove underground projects to Q3 2026.
  • Archimedes development remains on schedule with first gold expected in Q4 2026.
  • Current mineral resources at Archimedes include 1.8 million tonnes indicated and 4.2 million tonnes inferred.

i-80 Gold's latest assay results reinforce the high-grade potential of its Archimedes Underground Project, supporting its strategy to become a mid-tier gold producer through phased development. The company's focus on optimizing project sequencing and leveraging existing infrastructure highlights its approach to maximizing efficiency in Nevada's prolific gold-producing trends.

Resource Expansion
Whether the current drill program will further expand mineralization beyond existing boundaries.
Project Timing
The pace at which feasibility studies and permitting activities will progress for Archimedes and other projects.
Processing Flexibility
How the integration of oxide material into the mine plan may impact processing costs and efficiency.