Horizon Petroleum Moves Forward with Lachowice Gas Development in Poland

  • Horizon Petroleum finalized the contract for the Lachowice 7 well pad construction, with field operations set to begin in the second week of June 2026.
  • The company plans to start the Lachowice 7 well workover in July 2026, aiming for initial gas and/or electricity sales by late in the first half of 2027.
  • The Environmental Impact Assessment permit application for the early production facility has been submitted, with approval anticipated before year-end 2026.
  • Horizon has completed surveying for a 75 km² 3D seismic program, scheduled to commence in Q2 2027.

Horizon Petroleum's progress at the Lachowice gas development marks a critical step in its strategy to enhance energy independence and security in Europe. The company's focus on conventional natural gas resources aligns with broader industry trends toward stable, long-term energy solutions. Success at Lachowice could position Horizon as a key player in Poland's energy sector, with potential implications for regional energy markets and infrastructure development.

Execution Risk
Whether Horizon can successfully complete the Lachowice 7 well workover and achieve first cash flow by late in the first half of 2027.
Regulatory Approval
The timeline for the Environmental Impact Assessment permit approval and its impact on the project schedule.
Reserve Optimization
How the production data from the Lachowice 7 well will refine the wellbore completion design and optimize the field development plan.