Eramet Restarts Senegal Mineral Sands Production at 30% Capacity
Event summary
- Eramet partially restarted HMC production in Senegal at ~30% of nameplate capacity in late April 2026.
- 2026 production guidance set at 300-400 kt-HMC, down from previous estimates.
- Full production capacity expected to resume by Q1 2027 following reconstruction.
- Force majeure provisions remain in effect for customer and supplier contracts.
The big picture
Eramet's partial production restart in Senegal marks a critical step in recovering from the February 2026 fire. The gradual ramp-up reflects both the operational challenges of repairing damaged facilities and the strategic importance of maintaining supply in the mineral sands market. The company's ability to mitigate financial losses through insurance claims and temporary production solutions will be key to assessing the long-term impact of this disruption.
What we're watching
- Reconstruction Timeline
- Whether Eramet can meet its Q1 2027 target for full production capacity restoration.
- Financial Impact
- How the reduced production levels will affect 2026 operating income and insurance claims.
- Market Response
- Customer reactions to the partial restart and force majeure provisions.