EMP Metals Advances Project Aurora into Commissioning Phase

  • EMP Metals completed major site infrastructure and received all required permits for Project Aurora.
  • Commissioning activities are 50% complete, with first raw brine introduced on July 1, 2026.
  • Company secured non-dilutive government funding from BCIN Fund, NGen program, and SCMII.
  • Project Aurora is designed to process 10 m³/day of raw brine for lithium refining demonstration.

EMP Metals' progress on Project Aurora aligns with the growing emphasis on domestic lithium development and critical mineral processing. The company's ability to secure government support underscores the strategic importance of its Saskatchewan resource, which benefits from favorable brine chemistry and established infrastructure. This positions EMP to potentially become a key player in the direct lithium extraction market.

Commissioning Success
Whether EMP can complete commissioning and optimize integrated process by Q3 2026.
Data Generation
How the operational data from demonstration will support future commercial-scale development.
Government Support
The pace at which additional non-dilutive funding may be secured for Project Aurora.