Dynacor Advances Ecuador Plant Rehabilitation, Targets Q4 Gold Pour

  • Dynacor's Ecuador plant rehabilitation is 65% complete, with first ore feed scheduled for October 2026.
  • Senegal plant commissioning is complete, with initial gold pour preparations underway.
  • Peru ore inventory reduction is on track to reach 75% of historical average by Q4 2026.
  • US$9.5 million spent of US$22-25 million projected capital expenditure for 2026.
  • Commercialisation permit approved by ARCOM, pending MAE approval in Q4 2026.

Dynacor's expansion projects in Ecuador and Senegal represent strategic moves to diversify its gold processing operations beyond Peru. The company's focus on artisanal mining supply chains positions it uniquely in the responsible mineral sourcing space. Success in these expansion projects will be critical for meeting 2027 production targets and enhancing stakeholder value. The company's ability to secure renewable energy sources for its Ecuador plant also highlights its commitment to sustainable operations.

Execution Risk
Whether Dynacor can maintain its aggressive timeline for Ecuador plant commissioning and first gold pour in Q4 2026.
Regulatory Dynamics
The pace at which MAE approval for commercialisation permit will be granted and its impact on production schedules.
Production Scaling
How quickly Senegal plant can ramp up to full capacity and contribute to 2027 production targets.