Aya Gold & Silver Advances Boumadine Project with Feasibility Study and Updated PEA
Event summary
- Aya Gold & Silver has completed 102,111 meters of infill drilling as part of a 360,000-meter campaign for the Boumadine Project.
- The company is preparing to launch a competitive tender process for mining services contracts, expected to be completed in H1-2027.
- An updated Preliminary Economic Assessment (PEA) for Boumadine is on track for release in H2-2026.
- Metallurgical testwork program led by SGS Canada Inc. is in its final phase, optimizing process parameters and supporting final plant design.
The big picture
Aya Gold & Silver's progress on the Boumadine Project underscores its strategic focus on expanding its resource base in Morocco. The project's district-scale potential and polymetallic mineralization position it as a key asset in Aya's growth pipeline, aligning with broader industry trends of exploring underexplored regions for precious metals. The company's systematic approach to feasibility studies and economic assessments reflects a disciplined strategy aimed at de-risking long-term water supply and power infrastructure challenges.
What we're watching
- Project Timelines
- Whether Aya can maintain its aggressive timeline for completing the feasibility study by H2-2027 and starting early works by year-end.
- Contractor Selection
- How the competitive tender process for mining services will impact long-term operating partnerships and project costs.
- Market Conditions
- The pace at which updated metal prices and concentrate payable assumptions in the PEA reflect current market conditions, particularly strong sulfur demand.