Artemis Gold Boosts Q3 Production 14%, Eyes 2029 Capacity Triple

  • Blackwater Mine produced 69,546 ounces of gold in Q3 2026, up 14% YoY.
  • Year-to-date production at 205,532 ounces, on track for 265K–290K annual guidance.
  • Phase 1A expansion 77% complete, set for Q4 commissioning, boosting capacity by 33%.
  • Expanded Phase 2 (EP2) project advancing, targeting >500K ounces annually by 2029.

Artemis Gold's Q3 results underscore its aggressive expansion strategy amid a gold market that continues to favor producers with scalable, low-cost operations. The Phase 1A and EP2 projects position the company to more than triple processing capacity by 2029, aligning with broader industry trends toward consolidation and operational efficiency. Success hinges on maintaining production discipline while navigating regulatory and logistical challenges in British Columbia.

Execution Risk
Whether Phase 1A commissioning stays on track amid ongoing debottlenecking work.
Production Scaling
The pace at which Artemis can sustain throughput increases while maintaining recovery rates.
Market Dynamics
How sustained gold prices will impact the economic viability of the Blackwater Mine's expansions.