Allied Gold Advances Kurmuk Mine Toward Commercial Production
Event summary
- Allied Gold energized the 88-kilometer power line connecting the Kurmuk Mine to Ethiopia’s national grid.
- First ore was fed through the crushing circuit, marking a key operational milestone.
- Ore stockpiles have reached approximately one million tonnes, with plans to increase to 1.5 million tonnes.
- First gold production is expected soon after ore is introduced to the grinding circuit.
- The mine is projected to produce 240,000–270,000 ounces of gold in its first full year.
The big picture
Allied Gold’s Kurmuk Mine represents a strategic pivot toward large-scale, low-cost gold production in Ethiopia. The successful grid connection and initial ore processing mark critical steps in transitioning from commissioning to full operations, positioning the mine as a key growth driver for the company. The project’s scale—with projected annual production of 290,000 ounces at industry-leading costs—aligns with broader industry trends toward expanding African gold production amid rising global demand.
What we're watching
- Production Ramp-Up
- How the pace of ore stockpiling and circuit commissioning will affect the timeline for reaching full commercial production.
- Cost Efficiency
- Whether the fixed power rate of US$0.04 per kilowatt-hour will sustain the mine’s expected low production costs.
- Exploration Potential
- The pace at which exploration efforts will expand mineral inventories and extend the mine’s life beyond the initial 15-year target.